Skip to main content

Day 6 (7/17) production has been cancelled

Mike Cartwright
Social share icons

All,

 Day 6 (7/17) production has been cancelled for all shifts this weekend. Those required to work will be notified by their leader.

Final Process repair remains scheduled for day 6.

 The float reduction canvass sheets are now available for days 6 and 7, all 3 shifts. Please sign up to support.

 Trades across the site will remain scheduled for all 3 shifts on Day 6. Day 7 will remain voluntary.

 Friday Production is scheduled as follows:

3rd - 8 hours

1st - 9 hours

2nd - 9 hours (3:00 pm and 3:12 pm start times)

Thank you,

Lauren Addie

Arlington Assembly Plant

Desk: 817-652-2549

Cell: 682-219-6423